Notice of Temporary Traffic Lights Saltley Viaduct, Birmingham
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-31-19/03/2025
Work Item Summary
- Project Phase
- Phase 1
- Region
- Birmingham
- Location
- Saltley
- Worksite Name
- Saltley Viaduct
- Contractor
- BBV JV
- Type of works
- Traffic management
- Estimated Start Date
- 22/03/2025
- Estimated End Date
- 22/03/2025
What we are doing
Emergency Works
The temporary traffic barriers that are currently on Saltley Viaduct need replacing in order to keep road users and the public safe.
Temporary Traffic Lights
To carry this work out safely, we will need to put in place temporary traffic lights on a section of Saltley Viaduct. These will be operational from 11.00pm – 6.00am on Saturday 22 March. Pedestrian access and access to frontages will be maintained throughout.