View route map
Notice of temporary traffic management on B4118 Birmingham Road
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-14-16/07/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Water Orton
- Contractor
- BBV JV
- Type of works
- Construction, Traffic management
- Estimated Start Date
- 02/08/2021
- Estimated End Date
- 03/08/2021
What we are doing
In June 2021, we sent out a notification to outline that BBV would be completing the site access construction for our compound on the B4118 Birmingham Road. To continue these works we will now be completing some road surfacing on Monday 2 August 2021.
In order to carry out our works safely we will implement a temporary two-way traffic light system. Our temporary traffic lights will be in place from 9:30am – 3:30pm.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]