Notice of temporary traffic measures around Stonebridge Island in early 2022
Work item: HS2-EW-LM-Ph1-Ar-No-N1-Prog-works-36-16/12/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Solihull, Warwickshire, West Midlands
- Location
- Hampton in Arden
- Contractor
- LM JV
- Type of works
- Traffic management, Vegetation clearance
- Estimated Start Date
- 24/01/2022
- Estimated End Date
- 04/03/2022
What we are doing
As part of our preparation works for future construction of the HS2 railway route, we are undertaking roadside vegetation clearance. To safely carry out our works, we will install temporary traffic measures when necessary.
We will be working on and around Stonebridge Island, including sections of the A452, A446 and A45.
Subject to obtaining the relevant consents, we will be carrying out the following temporary traffic measures in January, February, and March:
- Temporary road closure of Packington Lane and lane closures along sections of the A446 and A452 southbound, from 09:30am to 3:30pm each weekday, between Monday 24 January to Friday 18 February.
- Temporary lane closures along sections of the A452 and A45 near Stonebridge Island, from 09.30am to 3.30pm each weekday, between Monday 21 February to Friday 4 March.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]