Notice of temporary two-way traffic lights on Uttoxeter Road, Blithbury.

Work item: HS2-EW-BB-Ph2A-Traf-44-13/02/2024

Work Item Summary

Project Phase
Phase 2a
Region
Staffordshire
Location
Blithbury, Uttoxeter Road
Worksite Name
Blithbury, Uttoxeter Road
Contractor
Balfour Beatty
Type of works
Drainage repairs, Vegetation clearance
Estimated Start Date
05/06/2024
Estimated End Date
21/06/2024

What we are doing

As part of our ongoing maintenance of sites along Uttoxeter Road, from 5th June to 21st June 2024, we will be carrying out works to drainage on land currently possessed by HS2.

On Wednesday 5th June and Thursday 6th June 2024 vegetation clearance at an existing gate will be undertaken to allow access to carry out the works. Temporary two-way traffic lights will be installed to enable these works to be undertaken safely.

The repairs to the drain will be carried out between Monday 17th June and Friday 21st June. We will need to install temporary two-way traffic lights to manage the safe movement of the vehicles in and out of the land.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]