Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Ickenham
- Contractor
- Thames Water
- Type of works
- Utility works / surveys
- Estimated Start Date
- 27/09/2021
- Estimated End Date
- 02/10/2021
What we are doing
Thames Water update
As part of our work, to divert our sewer to make way for the new HS2 railway, we need to carry out some trial holes and a sewer survey.
Trial Holes
From Monday 27 September, we will be carrying out trial holes off High Road – opposite the unused road next to the entrance of The Soldiers Return. Our work will take up to six days to complete.
The footpath will remain open for the duration of our works.
The road will remain open at all times, but we will need to close half of the northern lane. There will be traffic management in place to keep the traffic flowing.
Sewer Survey
We will be carrying out a CCTV survey of our survey on the private road of The Green on Tuesday 28 September. Our survey area is expected to cover the public green area opposite the houses.
Enabling work
We plan to start enabling works on Monday 4 October, subject to planning permission being granted by London Borough of Hillingdon with no planning conditions that would restrict such work commencing at that time.
Getting in touch
For all enquiries about the work Thames Water are doing on behalf of HS2, please use the below details and quote the reference number: BB 972617.
Phone: 0800 316 9800 (our lines are always open) Email: [email protected]
Download information relating to these works
Find out more about