Notice of Thames Water work

Work item: HS2-MW-TW-Ph1-Ar-So-S2-Prog-works-05-03/11/2021-2

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
Ickenham
Worksite Name
West Ruislip
Contractor
Thames Water
Type of works
Construction, Lane closure
Estimated Start Date
13/12/2021
Estimated End Date
24/12/2021

What we are doing

Thames Water update
We are working to divert our sewer to make way for the new HS2 railway. Following the London Borough of Hillingdon’s planning approval with planning conditions, we have received sign off, of some of the conditions. This means we can plan to build the entrance point of the temporary haul road off High Road, Ickenham.

New road entrance
Subject to approval from the London Borough of Hillingdon, we will carry out work from Monday 13 December until Friday 24 December. This will be to construct a new road entrance off High Road, next to the entrance of The Soldiers Return.

The footpath will remain open for the duration of our works.

The road will remain open at all times, but we will need to close half of the northern lane. There will be traffic management in place to keep the traffic flowing.

Future work
We will not be working over the Christmas period and the site will close from 24 December until 4 January 2022.
When we restart our work, we will continue to construct the temporary road from the new access point to the Ickenham Green allotments.

Getting in touch
For all enquiries about the work Thames Water are doing on behalf of HS2, please use the below details and quote the reference number: BB 972617.
Phone: 0800 316 9800 (our lines are always open) Email: [email protected]

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]