Notice of Thames Water work
Work item: HS2-MW-TW-Ph1-Ar-So-S2-Prog-works-05-03/11/2021-2
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Ickenham
- Worksite Name
- West Ruislip
- Contractor
- Thames Water
- Type of works
- Construction, Lane closure
- Estimated Start Date
- 13/12/2021
- Estimated End Date
- 24/12/2021
What we are doing
Thames Water update
We are working to divert our sewer to make way for the new HS2 railway. Following the London Borough of Hillingdon’s planning approval with planning conditions, we have received sign off, of some of the conditions. This means we can plan to build the entrance point of the temporary haul road off High Road, Ickenham.
New road entrance
Subject to approval from the London Borough of Hillingdon, we will carry out work from Monday 13 December until Friday 24 December. This will be to construct a new road entrance off High Road, next to the entrance of The Soldiers Return.
The footpath will remain open for the duration of our works.
The road will remain open at all times, but we will need to close half of the northern lane. There will be traffic management in place to keep the traffic flowing.
Future work
We will not be working over the Christmas period and the site will close from 24 December until 4 January 2022.
When we restart our work, we will continue to construct the temporary road from the new access point to the Ickenham Green allotments.
Getting in touch
For all enquiries about the work Thames Water are doing on behalf of HS2, please use the below details and quote the reference number: BB 972617.
Phone: 0800 316 9800 (our lines are always open) Email: [email protected]