Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Ickenham
- Worksite Name
- West Ruislip
- Contractor
- SCS JV
- Type of works
- Construction, Vegetation clearance, Worksite / compound set-up
- Estimated Start Date
- 01/02/2022
- Estimated End Date
- 31/03/2023
What we are doing
Thames Water update
We have received approval from London Borough of Hillingdon to discharge the pre-commencement planning conditions for the haul road. We will start to remove trees early February and will then set up the site offices and construct the bridge to cross the Ickenham stream.
Welfare units
Site units will be delivered and set up, on the land opposite The Green. The site will include welfare and office units, plus some parking bays.
Crossing Ickenham stream
As we progress with the haul road, we will need to put in a temporary bridge across the Ickenham stream. The bridge will be used by our site vehicles and will be located as per the map below.
Getting in touch
For all enquiries about the work Thames Water are doing on behalf of HS2, please use the below details and quote the reference number: BB972617. Phone: 0800 316 9800 (our lines are always open) Email: [email protected]