Notice of Thames Water work – The Greenway construction road
Work item: HS2-MW-UT-Ph1-OOC-St-S4-UT-15-14/12/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Ruislip, The Greenway
- Worksite Name
- West Ruislip
- Contractor
- Thames Water
- Type of works
- Haul road construction
- Estimated Start Date
- 04/01/2022
- Estimated End Date
- 22/01/2022
What we are doing
Thames Water update
We are working to divert our sewer to make way for the new HS2 railway. We are due to complete the entrance for the new haul road off High Road, Ickenham before Christmas. When we return to site in the new year, we will be starting phase two.
Phase two
We will commence phase two of the haul road from Tuesday 4 January for up to three weeks. Phase two will go from the edge of the new entrance point, to the edge of the green area opposite The Green.
The footpath from the road up to the allotments will remain open. The footpath across the entrance point to the road will be closed, but the footpath on the other side of the road will remain open.
Future work
We will write to you again before we start phase three of the haul road.
Getting in touch
For all enquiries about the work Thames Water are doing on behalf of HS2, please use the below details and quote the reference number: BB 972617.
Phone: 0800 316 9800 (our lines are always open) Email: [email protected]
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]