Work item: HS2-MW-TW-Ph1-Ar-CA-S1-Prog-works-1-27/09/2021

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Adelaide Road
Worksite Name
Adelaide Road
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
12/10/2021
Estimated End Date
31/10/2021

What we are doing

Thames Water update
As part of HS2’s enabling work, Thames Water are required to access shafts on the Thames Lee Tunnel (TLT), to assess the condition of our existing asset that may be affected by HS2’s tunneling works.

Our work
We need to access and survey a Thames Lee Tunnel (TLT) shaft inside our site Barrow Hill Reservoir.
Our work will start on Tuesday 12 October and will take approximately two weeks.

To carry out a survey in the shaft we need to pump out all the water out. This means there we need to send a HGV to site, and we will need to suspend a parking bay – so the vehicle can enter and leave the site safely.