Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Mornington Crescent
- Contractor
- SCS JV
- Type of works
- Railway systems
- Estimated Start Date
- 27/09/2020
- Estimated End Date
- 30/04/2021
What we are doing
We will carry out overnight activities next to Network Rail tracks near Hampstead Road, Granby Terrace and Mornington Street bridges. From the end of September we will start installing hoarding near Mornington Street bridge at track level between our worksite and the rail tracks. The works are carried out at night along with planned Network Rail works during track closures for safe working.
For more details on these works please download the PDF notice below.
Download information relating to these works