Notice of traffic lights and road closures, A422, Westbury March update

Work item: HS2-EKFB-26-1889

Work Item Summary

Project Phase
Phase 1
Region
Northamptonshire
Location
Westbury
Worksite Name
A422 Westbury
Contractor
EKFB JV
Type of works
Road closure, Traffic management, Utility Works
Estimated Start Date
17/04/2026
Estimated End Date
31/05/2026

What we are doing

Utilities in the area need to be redirected because of the new overbridge.

Location
A422, Westbury.

Duration

Road closures –

Friday 8:00pm to Monday 5:30am

  • 17 April to 20 April 2026
  • 24 April to 27 April 2026
  • 08 May to 11 May 2026
  • 15 May to 18 May 2026
  • 28 May to 31 May 2026

Traffic management

  • 20 April to 26 April 2026
  • 11 May to 22 May 2026

What to expect

  • Weekend road closures and lane closures with traffic management.

We will aim to remove traffic management when safe to do so. When traffic management is in place please allow extra journey time and expect delays.

HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]