Update – Notice of traffic lights on Ashow Road and Crewe Lane, Stoneleigh

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-23-21/06/2024

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Stoneleigh
Contractor
BBV JV
Type of works
Utility works / surveys
Estimated Start Date
12/08/2024
Estimated End Date
04/10/2024

What we are doing

We will be carrying out utility diversion works at the junction of Ashow Road and Crewe Lane, to create the highway drainage and to install a 11kv connection cable. There will be three-way temporary traffic management in place from 8am to 6pm.

We previously informed you that this work would be carried out in two phases

  • Phase one – 12 August to 6 September 2024
  • Phase two -18 September to 21 September 2024

Works are now scheduled to be completed as a single phase of work but have been extended until 4 October.

  • 12 August to 4 October 2024 – temporary three- way traffic lights will be in place from 8am to 6pm each day.

To minimise local disruption, there will be advanced warning signs placed on B4115.