Notice of traffic management, A418 Oxford Road

Work item: HS2-MW-EK-Ph1-Ar-Ce-Traf-26-20/01/2025

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Contractor
EKFB JV
Type of works
Traffic management
Estimated Start Date
03/02/2025
Estimated End Date
12/02/2025

What we are doing

In February, we will adding road priorities at two junctions along the new A418 Oxford Road alignment. We will be carrying out ‘white lining’ works and installing signage under temporary traffic management over the course of 2 days as two different locations on the new road alignment. There will be Traffic management on Monday 3 February and Wednesday 12 February from 9:30am-3pm.