POSTPONED traffic management at the crossroads of Station Road North, Station Road South and Quainton Road

Work item: HS2-EKFB-25-1036

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Quainton
Worksite Name
Station Road North, Station Road South and Quainton Road
Contractor
EKFB JV
Type of works
Traffic management
Estimated Start Date
19/05/2025
Estimated End Date
12/09/2025

What we are doing

UPDATE These works have been postponed we will update you in due course.

We need to install temporary traffic lights in order to complete the diversion of Thames Water utilities at the crossroads of Station Road North, Station Road South and Quainton Road. These works are to facilitate the upcoming Station Road realignment.

There will be multi-phase traffic lights in place from Monday 19 May 2025 to Friday 12 September 2025.