Notice of traffic management – Coleshill Heath Road
Work item: HS2-EW-BBV-Ph1-Ar-No-N2-Traf-6-15/09/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Solihull, West Midlands
- Location
- Coleshill Heath Road
- Contractor
- BBV JV
- Type of works
- Traffic management
- Estimated Start Date
- 18/06/2022
- Estimated End Date
- 18/06/2022
What we are doing
We will be finalising the work to our new construction site entrance on Coleshill Heath Road. To do this safely we will install temporary traffic lights on Coleshill Heath Road either side of the site entrance. Safe pedestrian access will be maintained by using a temporary pedestrian barrier.
The temporary lights will be in place from 8:00am until 1:00pm on Saturday 18 June for one day only. Our workforce maybe on site one hour before and one hour after to set up and secure our equipment.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]