Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Gawcott Road
- Worksite Name
- Calvert
- Contractor
- EKFB JV
- Type of works
- Traffic management
- Estimated Start Date
- 23/10/2025
- Estimated End Date
- 29/10/2025
What we are doing
Towards the end of October there will be 3-way temporary traffic lights in place on Gawcott Road, Calvert. These will be in place to facilitate the Anglian Water asset connection to the existing pipe, including excavation, pipe and valve installation, backfilling and compaction.
The traffic management will be in place from Thursday 23 October to Wednesday 29 October 2025. These dates may be subject to change due to circumstances outside of our control, such as weather.