Notice of Traffic Management, Gawcott Road/Perry Hill
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-27-24/10/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Buckinghamshire
- Worksite Name
- Gawcott Road
- Contractor
- EKFB JV
- Type of works
- Gas Main Works, Traffic management
- Estimated Start Date
- 22/01/2024
- Estimated End Date
- 04/02/2024
What we are doing
At the end of January 2024, we will be carrying out some works on the temporary gas main diversion on Gawcott Road by completing some gas trial holes. These works are planned to be completed under 2-way lights.
To carry out these works safely and effectively, a section of Gawcott Road/Perry Hill will require traffic management.
These works are an important step towards the re-alignment of Gawcott Road/Perry Hill over the new bridge, currently under construction.
When will these works take place?
A section of Gawcott Road/Perry Hill will be under traffic management from Monday 22 January until Sunday 4 February 2024, near to the entrance of the EKFB compound.
These dates may be subject to change due to circumstances outside of our control, such as weather.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]