Notice of Traffic Management in the vicinity of Portway Road, Twyford
Work item: HS2-EKFB-25-1388
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Twyford
- Worksite Name
- Portway Road
- Contractor
- EKFB JV
- Type of works
- Traffic management
- Estimated Start Date
- 15/10/2025
- Estimated End Date
- 02/11/2025
What we are doing
From 15 October there will be 2-way, followed by 3-way temporary traffic lights in place on Portway Road, Twyford and the junction with the Twyford to Steeple Claydon Road. These will be in place to facilitate the excavation of trial holes, in advance of the long-term closure of the Twyford to Steeple Claydon road later in 2025.
The traffic management will take place in three phases, as follows;
• 15 – 19 October – 2-way lights
• 23 – 28 October – 2-way lights
• 28 October – 2 November – 3-way lights.