Updated notice of traffic management on A4091 and Bodymoor Heath Lane

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-13-13/02/2023

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire, West Midlands
Location
Bodymoor Heath
Contractor
BBV JV
Type of works
Lane closure
Estimated Start Date
11/04/2023
Estimated End Date
25/04/2023

What we are doing

We are carrying out works to create a safe access into our compound, at Middleton House Farm, off the A4091. To complete this access we will need  along a section of the A4091 carriageway.
We will also undertake work on Bodymoor Heath Lane to install traffic signage for our site access.

To ensure we can complete these works safely we will install temporary traffic management at these locations.

To complete these works safely we will require the following traffic management:

A4091

Single lane closure with temporary three-way traffic lights (24 hours) on the A4091 and the access into our compound at Middleton House Farm on:

• Tuesday 11 April to Sunday 16 April 2023.

We will also close the layby at this location, on the A4091, over this period.

Bodymoor Heath Lane

Single lane closure on Bodymoor Heath Lane with temporary two-way lights between 9.30am to 3.30pm on:

• Monday 24 April to Tuesday 25 April 2023.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]