Notice of traffic management on A4091 and Bodymoor Heath Road
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-10-13/02/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire, West Midlands
- Location
- Bodymoor Heath
- Contractor
- BBV JV
- Type of works
- Traffic management
- Estimated Start Date
- 13/03/2023
- Estimated End Date
- 17/04/2023
What we are doing
Before we can construct the new railway we will be diverting underground utilities along the A4091 and Bodymoor Heath Road. While we complete these works we will excavate a section of the carriageway and complete works in the verges.
To carry out these works safely we will install a single lane closure on the A4091 and Bodymoor Heath Road from Monday 13 March to Monday 17April 2023. During this period, we will have temporary three-way traffic lights in place 24 hours a day.
Download information relating to these works