What we are doing
**Update**
Overnight closures of the A425 Southam Road will now be in place, between the B4452 and the B4451, from 8 January 2024 to 16 February 2024. This section of road will be closed between 8pm to 6am (Sunday -Thursday). A signed diversion route will be in place.
Temporary traffic lights: Outside of the overnight closure period we will operate multi-way temporary traffic lights on the A425 Southam Road from 8 January 2024 to 16 February 2024. During peak times we will manually control the traffic lights to manage traffic flows.
We will maintain access to properties at all times during these works.
We will be undertaking utility diversion works on the A425 Southam Road to enable the construction of the new green tunnel. To complete these works safely we will install overnight road closures and temporary traffic lights during the daytime.
Overnight closures of the A425 Southam Road will be in place, between the B4452 and the B4451, from 8 January 2024 to 6 February 2024. This section of road will be closed between 8pm to 6am (Mon-Fri). A signed diversion route will be in place (please see map on notification).
Temporary traffic lights: Outside of the overnight closure period we will operate multi-way temporary traffic lights on the A425 Southam Road from 8 January 2024 to 16 February 2024. During peak times we will manually control the traffic lights to manage traffic flows.
We will maintain access to properties at all times during these works. Our workforce may be on site up to one hour before and one hour after to set up and secure our equipment.