Notice of traffic management on A446, near Coleshill
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-41-09/07/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Coleshill
- Contractor
- BBV JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 31/10/2022
- Estimated End Date
- 09/12/2022
What we are doing
To continue preparation for the construction of the Chattle Hill Structure, BBV will complete utility diversion works on the junction of the A446 and Watton Lane, near Coleshill. We previously sent out a notification outlining traffic management from Monday 3 October until Friday 4 November to complete these works. However, due to unforeseen circumstances, these works will now be complete from Monday 31 October until Friday 9 December.
In order to complete these works safely, we will implement a 24-hour, three-way traffic light system throughout these works. (Location shown on map below). This traffic management will be in place 24 hours a day due to the excavation work that will need to be completed. The traffic lights will be manually operated throughout the hours of 7am until 7pm, to ensure traffic flows as freely as possible.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]