Notice of traffic management on A446, Watton Lane and Gorsey Lane, Coleshill

Work item: HS2-MW-BBV-Ph1-Ar-No-N2-Traf-36-29/01/2023

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire, West Midlands
Location
Coleshill
Contractor
BBV JV
Type of works
Ground investigations, Overnight road closure, Traffic management
Estimated Start Date
17/04/2023
Estimated End Date
30/06/2023

What we are doing

To continue to prepare for our works to construct the Chattle Hill Structure, that will carry the HS2 railway over the A446, we will complete trial holes on sections of the A446 and Gorsey Lane. Trial holes are created to assess the condition of the ground prior to construction. As well as this, we will also complete utility diversions along the A446 and Watton Lane.

To complete the trial hole works safely, we will install seven overnight closures along sections of the A446 and Gorsey Lane. The works will take place from Monday 17 April until the morning of Wednesday 26 April, with closures installed from 8.00pm until 5.00am each evening. No work will take place overnight on Saturday 22 April or Sunday 23 April. Residents access will be maintained throughout, there will be a diversion whilst the closure is in place and access to Gorsey Lane will be maintained at all times via traffic marshals.