Notice of traffic management on A46 Kenilworth Bypass

Work item: HS2-MW-EK-Ph1-Ar-No-N2-Prog-works-47-19/04/2024

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Stoneleigh
Contractor
BBV JV
Type of works
Road repairs
Estimated Start Date
21/05/2024
Estimated End Date
23/05/2024

What we are doing

The work we will be doing We are constructing a box structure to take the A46 in Kenilworth over the new HS2 line. We recently notified you of our previous phase of work taking place in April. As part of the next phase of our programme we need to complete some further works, which includes:
• Installing temporary vehicle restraint systems to support the flow of traffic and ensuring the safety of our workforce
• Installing CCTV to monitor the flow of traffic
• Widening the embankment next to the carriageway
• Realigning drainage ahead of carriageway drainage work later in our programme.
To complete our work safely, we will fully close the northbound and southbound carriageways overnight between Thickthorn Roundabout and A45 Stivichall Interchange on the following dates:
• Northbound carriageway closure on 21 May from 8pm until 6am on 22 May to install the temporary vehicle restraint system.
• Southbound carriageway closure on 22 May from 8pm until 6am on 23 May to install the temporary vehicle restraint system. We will also extend the lane one closure currently in place by Warwickshire County Council during the southbound overnight closure.
Once Warwickshire County Council works are complete, lane one restrictions will remain in place in both directions until October 2024 while we complete our work.

We will be working on the A46 Kenilworth Bypass between the Thickthorn Roundabout and A45 Stivichall Interchange.

Download information relating to these works