Notice of traffic management on A46 Kenilworth Bypass
Work item: HS2-MW-EK-Ph1-Ar-No-N2-Prog-works-47-19/04/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Stoneleigh
- Contractor
- BBV JV
- Type of works
- Road repairs
- Estimated Start Date
- 21/05/2024
- Estimated End Date
- 23/05/2024
What we are doing
The work we will be doing We are constructing a box structure to take the A46 in Kenilworth over the new HS2 line. We recently notified you of our previous phase of work taking place in April. As part of the next phase of our programme we need to complete some further works, which includes:
• Installing temporary vehicle restraint systems to support the flow of traffic and ensuring the safety of our workforce
• Installing CCTV to monitor the flow of traffic
• Widening the embankment next to the carriageway
• Realigning drainage ahead of carriageway drainage work later in our programme.
To complete our work safely, we will fully close the northbound and southbound carriageways overnight between Thickthorn Roundabout and A45 Stivichall Interchange on the following dates:
• Northbound carriageway closure on 21 May from 8pm until 6am on 22 May to install the temporary vehicle restraint system.
• Southbound carriageway closure on 22 May from 8pm until 6am on 23 May to install the temporary vehicle restraint system. We will also extend the lane one closure currently in place by Warwickshire County Council during the southbound overnight closure.
Once Warwickshire County Council works are complete, lane one restrictions will remain in place in both directions until October 2024 while we complete our work.
We will be working on the A46 Kenilworth Bypass between the Thickthorn Roundabout and A45 Stivichall Interchange.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]