Notice of traffic management on A453 Sutton Road and Drayton Lane
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-5-25/10/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Staffordshire
- Location
- Drayton Bassett
- Contractor
- BBV JV
- Type of works
- Road closure, Utility works / surveys
- Estimated Start Date
- 16/11/2022
- Estimated End Date
- 24/02/2023
What we are doing
BBV will be undertaking surveys and diverting underground utilities on the A453 Sutton Road and Drayton Lane. We will complete surveys to locate utilities in the highway and the verges at this location. Once we have completed our survey works, we will begin diverting the utilities ahead of the construction of the new railway. These works will require us to excavate a section of the A453 Sutton Road and Drayton Lane. To ensure we can complete these works safely we will install temporary traffic management to manage the flow of traffic and ensure the safety of road users.
We will complete these works from 14 November 2022 until Friday 24 February 2023. We will install:
A lane closure with temporary traffic lights (24-hour a day) on:
• A453 Sutton Road / Drayton Lane – 15 November 2022 to 23 December 2022.
A temporary closure (24 hours) on:
• Drayton Road – 09 January 2023 to 22 January 2023
Due to circumstances beyond our control the following dates have been revised.
A lane closure with temporary traffic lights (24-hour a day) on:
• A453 Sutton Road / Drayton Lane 23 January 2023 to 10 February 2023.
A lane closure with temporary three-way traffic lights (24-hour a day) on:
• A453 Sutton Road / Drayton Lane – 13 February to 24 February 2023.
Download information relating to these works