Update notice of traffic management on and around Coleshill Heath Road
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-25-22/11/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Solihull
- Location
- Coleshill Heath Road
- Contractor
- BBV JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 04/01/2023
- Estimated End Date
- 17/01/2023
What we are doing
We previously informed you that the that temporary traffic lights would be in operation on Heath Park Island overnight from Monday 9 January until Friday 13 January. Unfortunately, this work has taken longer that we had hoped, and the lights will need to be in operation for a further two nights on Monday 16 January and Tuesday 17 January.
In order for the new railway to pass over the M6 an embankment is being built on part of Heath Park and Coleshill Heath Road. This will require several utilities to be diverted, so that our works do not interfere with the supply. To do this, we will need to close the A452 Chester Road overnight between Birmingham Business Park and Heath Park Island, followed by temporary traffic lights on Heath Park Island.