Notice of traffic management on Attleboro Lane for utility crossings

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-15/07/2024

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire, West Midlands
Location
Coleshill
Contractor
BBV JV
Type of works
Traffic management
Estimated Start Date
05/08/2024
Estimated End Date
13/09/2024

What we are doing

To prepare for our continued construction in the area, BBV will be installing three road crossings and electric cables on Attleboro

To complete the works safely, we will install traffic management from 5 August to 13 September. The traffic management will be in place 24 hours a day, seven days a week. Our working hours will be from 8am to 6pm.

Access to properties will be maintained at all times.