Revised notice of traffic management on B4114 Birmingham Road, Coleshill
Work item: HS2-MW-BBV-Ph1-Int-St-N3-Traf-44-29/03/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Coleshill
- Contractor
- BBV JV
- Type of works
- Haul road construction, Traffic management
- Estimated Start Date
- 26/06/2023
- Estimated End Date
- 01/07/2023
What we are doing
Revised notice
We are continuing to prepare for works to construct the Coleshill Viaducts that will carry the HS2 railway over the existing B4114 Birmingham Road. We previously sent out a notification outlining traffic management that would take place from Monday 22 May until Friday 23 June to widen and create site accesses on the south side of the B4114 Birmingham Road. Due to unforeseen circumstances this work has now been delayed and will be complete in two phases. Phase one will take place from Monday 26 June until Saturday 1 July, to widen our existing site access. We will update further on phase two of the works
We are continuing to prepare for works to construct the Coleshill Viaducts, that will carry the HS2 railway over the existing B4114 Birmingham Road. This includes setting up our works areas and compounds.
Subject to consent, we will widen our existing site access on the south side of the B4114 Birmingham Road and create a fourth arm off the existing B4114 Birmingham Road roundabout. This work will take place from Monday 22 May until Friday 23 June. Our working hours will be 8.00am until 6.00pm Monday to Friday.
To complete this work safely, we will install three-way traffic lights along B4114 Birmingham Road, this will include the roundabout. The traffic lights will be in place from Monday 22 May until Friday 23 June, 24 hours a day. During peak hours the traffic lights will be manually controlled in order to reduce disruption to traffic.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]