UPDATED Notice of Traffic Management on Brackley Lane, Calvert Green

Work item: HS2-EKFB-25-1041

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Brackley Lane
Worksite Name
Calvert
Contractor
EKFB JV
Type of works
Traffic management
Estimated Start Date
30/06/2025
Estimated End Date
11/08/2025

What we are doing

We need to complete the tie-in of the new temporary link road onto the existing carriageway, including the excavation of trial holes for utilities works. To regulate the traffic flow, we require traffic management while these works are taking place.

The temporary traffic lights will be in place between 30 June until 11 August 2025 from 8.30am to 5.30pm