Notice of traffic management on Church Lane, Middleton
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-1-07/12/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire, West Midlands
- Location
- Middleton
- Contractor
- BBV JV
- Type of works
- Traffic management
- Estimated Start Date
- 29/01/2024
- Estimated End Date
- 09/02/2024
What we are doing
We will be undertaking works to prepare for a utility diversion along Church Lane, Middleton.
These works will require us to locate and survey utilities that are underneath the ground then assess the condition ahead of further works. To ensure we can complete these works safely we will install temporary traffic management to create a safe working area and ensure the safety of road users.
When the work will take place
To complete these works safely we will install temporary three-way traffic lights between Church Lane and Crowberry Lane from Monday 29 January to Friday 9 February between 9am to 4pm Monday to Friday only.