Notice of traffic management on Gilson Road (revised dates)
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-12-01/06/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire, West Midlands
- Location
- Gilson
- Contractor
- BBV JV
- Type of works
- Survey
- Estimated Start Date
- 18/07/2022
- Estimated End Date
- 19/07/2022
What we are doing
The work we will be completing
BBV were set to complete drainage surveys on Monday 20 June and Tuesday 21 June. Unfortunately, these works were delayed. We will now complete drainage survey works in areas of Gilson Road on Monday 18 July and Tuesday 19 July.
In order for us to carry out works safely, we will implement a two-way traffic light system on Gilson Road during this period. These traffic lights will be used in a rolling system, completing 150 metre sections at a time. There may also be short durations of three-way traffic lights where Gilson Road meets Watton Lane.
The traffic management will be in place from 9.30am until 3.30pm each day.