Work item: HS2-MW-BBV-Ph1-Ar-No-N2-Traf-11-06/06/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire, West Midlands
- Location
- Long Itchington
- Contractor
- BBV JV
- Type of works
- Traffic management
- Estimated Start Date
- 22/07/2024
- Estimated End Date
- 16/08/2024
What we are doing
*Updated notice
The traffic management will still be in place from 22 July to 16 August 2024 and will now be installed in the following phases:
- Phase one: 22 July to 26 July 2024: four-way temporary traffic lights will be in place 24 hours a day.
- Phase two: 29 July to 2 August 2024: full closure will be in operation between 8am to 6pm (Mon-Fri) with traffic lights overnight.
- Phase three: 5 August to 9 August 2024: temporary four-way traffic lights will be in place from 8am to 6pm each day.
- Phase four: 12 August to 16 August 2024: temporary four-way traffic lights will be in place from 8am to 6pm each day.
There will be no traffic management at the weekends.*
As we progress construction of the HS2 railway in the area we need to complete a range of surveys, including topographical, ecological, GPR and trial holes, on the carriageway and verges at the junction of Welsh Road and Long Itchington Road.
Some of these surveys will be completed using temporary traffic lights, with other surveys like trial holes, requiring a road closure.
The traffic management will be in place from 22 July to 16 August 2024 and will be installed in the following phases:
Phase 1: 22 July to 2 August 2024: Temporary traffic lights will be in operation between 8am to 6pm, Monday to Friday.
There will be no traffic management on weekends.
Phase 2: 5 August to 16 August 2024: A road closure of will be in place Monday to Friday from 8am to 6pm. Outside of these hours temporary traffic lights will be in operation from 6pm to 8am (Mon-Fri) and 24/7 on weekends.
During the closure there will be no through route from Offchurch to the Fosse Way. The Offchurch Greenway car park will only be accessible from The Fosse Way.
Download information relating to these works
- Notice of traffic management on Long Itchington Road and Welsh Road, Offchurch
- Updated notice of traffic management on Long Itchington Road and Welsh Road, Offchurch
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]