Updated notice of traffic management on the A446 Lichfield Road, Coleshill

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-17-24/02/2024

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire, West Midlands
Location
Coleshill
Worksite Name
A445 Lichfield Road
Contractor
BBV JV
Type of works
Lane closure, Utility works / surveys
Estimated Start Date
18/03/2024
Estimated End Date
23/06/2024

What we are doing

*Updated notice

Due to unforeseen circumstances, the program for these works has been rescheduled and will now end on 23 June 2024.

UPDATED: Due to unforeseen circumstances, these works have been delayed and will now end on Sunday 9 June. The lane closures and traffic lights will be in place 24 hours a day, seven days a week, however our working hours will start at 8am and finish at 6pm each weekday.

To continue our preparation for the construction of the HS2 railway, we will be diverting utilities along the A446 Lichfield Road. To complete these works safely we will be installing a lane closure and temporary traffic lights on the A446 Lichfield Road and Watton Lane.

The work will take place from Monday 18 March to Sunday 26 May. The lane closure and traffic lights will be in place 24 hours a day, seven days a week, however our working hours will start at 8am and finish at 6pm each weekday.