Notice of traffic management Rugby Road, Cubbington

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-21-19/09/2022

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire, West Midlands
Location
Cubbington
Worksite Name
Rugby Road
Contractor
BBV JV
Type of works
Road closure, Traffic management, Utility works / surveys
Estimated Start Date
19/09/2022
Estimated End Date
03/02/2023

What we are doing

Owing to several utilities needing to be moved across Rugby Road, we need to control the traffic in this area. To carry out this work safely the traffic will be controlled in four phases. Due to unexpected ecology issues the below phase’s have been revised.

Phase one: Will require two-way temporary traffic lights in place 24 hours a day seven days a week, operating for 3 weeks, from Tuesday 20 September 2022 to Monday 10 October 2022.

Phase two: Will require a full road closure 24 hours a day seven days a week from Monday 10 October 2022 to Friday 4 November 2022. A full diversion will be in place during this time.

Phase three: Will require two-way temporary traffic lights in place 24 hours a day seven days a week, operating for 6 weeks, from Friday 4 November to Friday 16 December 2022.

Phase four: Will require two-way temporary traffic lights in place 24 hours a day seven days a week, operating for 4 weeks, from Monday 9 January to Friday 3 February 2023.

Access to all properties will be maintained throughout.

Our working hours will be from 8am to 6pm Monday to Friday. Some Saturday working may be required from 8am to 1pm.
Our workforce maybe on site one hour before and one hour after to set up and secure our equipment.