Notice of Traffic Management, Station Road, Quainton
Work item: HS2-MW-EK-Ph1-Ar-Ce-C3-Traf-13-09/08/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Quainton
- Contractor
- EKFB JV
- Type of works
- Traffic management
- Estimated Start Date
- 05/09/2023
- Estimated End Date
- 09/09/2023
What we are doing
In September 2023 there will be a lane closure on Station Road to complete some core samples of the pavement and undertake compaction tests ahead of the Station Road realignment works starting later this year. In order to carry out these works safely and effectively, a section of Station Road, will be under 2-way temporary traffic lights. From Tuesday 5 September to Friday 8 September 2023.