Notice of Traffic Management, Steeple Claydon Road, Twyford Road, West Street and Gawcott Road
Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Traf-07-30/01/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Steeple Claydon
- Worksite Name
- Gawcott Road, West Street
- Contractor
- EKFB JV
- Type of works
- Gas Main Works, Traffic management
- Estimated Start Date
- 05/02/2024
- Estimated End Date
- 17/03/2024
What we are doing
At the beginning of February 2024, we will be carrying out some works on the temporary gas main diversion by completing some gas trial holes. These works are planned to be completed under 4-way lights.
To carry out these works safely and effectively, there will be traffic lights at the crossroads of Steeple Claydon Road, Twyford Road, West Street and Gawcott Road. These works are an important step towards the re-alignment of Gawcott Road/Perry Hill over the new bridge, currently under construction.
When will these works take place?
Steeple Claydon Road, Twyford Road, West Street and Gawcott Road crossroads will be under traffic management from Monday 5 February until Sunday 17 March 2024 near to the EKFB compound.
These dates may be subject to change due to circumstances outside of our control, such as weather.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]