Notice of trial hole surveys, Hanchurch Interchange, M6 J15

Work item: HS2-EW-BB-Ph2a-Ar-Surv-2-30/05/2022

Work Item Summary

Project Phase
Phase 2a
Region
Staffordshire
Location
Hanchurch Interchange, M6 J15, Newcastle Road, Whitmore Road
Worksite Name
Hanchurch Interchange, M6 J15, Newcastle Road, Whitmore Road
Contractor
Balfour Beatty
Type of works
Utility works / surveys
Estimated Start Date
21/06/2022
Estimated End Date
26/06/2022

What we are doing

What we are doing

HS2 Ltd is proposing to make highway improvements at the Hanchurch Interchange, M6 J15, Newcastle Road and the junction with Trentham and Whitmore Road. This is to improve traffic flows during the construction of HS2. To design the changes, Balfour Beatty will need to carry out utility surveys in this area from 21 to 26 June 2022.

The majority of these surveys will take place off the carriageway at Clayton Road, Ferndown Nature Reserve and on land east of Newcastle Road. However, we also need to undertake one trial hole on Newcastle Road, south of the Trentham and Whitmore Road junction.

To carry out this work safely, we will close the northbound carriageway on Newcastle Road (south) and put five-way temporary traffic lights in place at the junction of Newcastle Road and Whitmore Road.

When the work will take place

The lane closure and five-way temporary traffic lights will be in place on Sunday 26 June 2022 between 8am to 5.30pm

We will work hard to complete the works as quickly as possible to reduce disruption.

How this may affect you

To carry out the surveys, we will hand dig a trial hole and confirm the location of utility services, there may be some low-level noise when we undertake this work.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]