Update on two 24-hour concrete pours at Mandeville Road Site
Work item: HS2-MW-SCS-Ph1-Ar-So-S1-Ex-Mat-37-08/08/2023_02
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Mandeville Road
- Worksite Name
- Mandeville Road
- Contractor
- SCS JV
- Type of works
- Concrete pours
- Estimated Start Date
- 21/11/2023
- Estimated End Date
- 21/11/2023
What we are doing
What we are doing
On the 8 November we let you know that that the concrete pours that were due to take place on 9 November and 1 December 2023, would not go ahead as planned. We had to postpone the deliveries due to other works being delayed on site.
The new date for the first delivery will be on the afternoon of the 21 November. The second date is still to be confirmed but is likely to be between 4 and 11 December.
The pours will take place at the base of the main shaft, about 35 metres below ground level, which is where the noisiest activities will occur. While on-site work is not expected to cause additional disruption, more delivery vehicles will be present due to the quantity of concrete that is required.
Traffic Marshals will guide delivery vehicles as usual. Night-time work will not include noisy activities at ground level, with site lighting directed away from neighbouring homes. Noise and vibration monitoring will continue, with extra noise suppression if needed.
We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]