Notice of UKPN Construction Works
Work item: : HS2-MW-UT-Ph1-Ar-So-S2-UT-34-26/09/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak
- Worksite Name
- Old Oak Common
- Contractor
- UK Power Networks
- Type of works
- Construction
- Estimated Start Date
- 21/11/2022
- Estimated End Date
- 05/12/2022
What we are doing
What are we doing?
In order to prepare for the future railway, UK Power Networks (UKPN) need to carry out electricity cable installation works within the Willesden Euro-terminal site.
UKPN will be undertaking a trial bore hole as part of the micro-tunnel feasibility works, to determine a fixed route for UKPN’s cable route. They will then back fill their excavations and reinstate the area around to return it to its former state. All relevant consents/site access from associated stakeholders/landowners will have been obtained prior to the commencement of work.
UKPN will be working from Monday 21 November for 15 days.
How will this impact you?
UKPN will be working in the area highlighted on the map on page 2.
UKPN has a responsibility for delivering electricity services to homes and businesses across the region and will ensure that the impact of any work is kept to a minimum. There will be no impact to your electricity supply.