Notice of UKPN Construction Works at Atlas Road

Work item: HS2-MW-UKPN-Ph1-Ar-So-S1-Prog-works-1-08/09/2023

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing, Old Oak and North Acton
Location
Atlas Road
Worksite Name
Atlas Road
Contractor
SCS JV, UK Power Networks
Type of works
Cable works, Electrical Works
Estimated Start Date
18/10/2023
Estimated End Date
15/12/2023

What we are doing

Between 18 October and 15 December 2023, UK Power Networks (UKPN) will be carrying out electric cable installation works within the Network Rail Site.  This will support the delivery of power to the Tunnel Boring Machines when we start the construction of the new HS2 tunnels.