Notice of UKPN Construction Works at Willesden Euroterminal
Work item: HS2-MW-UKPN-Ph1-Ar-So-S1-Prog-works-5-11/12/2023-2
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, Old Oak and North Acton
- Location
- Willesden Euroterminal
- Worksite Name
- Willesden Euroterminal site
- Contractor
- SCS JV
- Type of works
- Cable works, Electrical Works
- Estimated Start Date
- 30/03/2024
- Estimated End Date
- 20/05/2024
What we are doing
The electricity cable ducts have now been installed and we will be returning to open excavations at intervals along the route. These open excavations will allow us to continue with the cable installation works we earlier informed you off.
From 30 March 2024 to 20 May 2024, UK Power Networks (UKPN) will be carrying out electricity cable installation works across four worksites.
Whilst we may not be working in every area at the same time, the excavations will need to remain open for the duration of our work. The area will then be backfilled and restored once the works have been completed.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]