Skip to main page content
View route map

Upcoming works in the Camden Cutting area; utility surveys, trial holes, monitoring equipment and lane closures

Work item: HS2-EW-SCS-Ph1-Ca-S1-OTH-7-02/11/2021

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Park Village East
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
01/03/2021
Estimated End Date
31/05/2021

What we are doing

Update: Utility surveys – 12 to 14 May

We recently carried out CCTV drainage surveys on streets surrounding the Camden Cutting, to assess the location and condition of underground utility services. Due to UKPN works in the area, we were unable to carry out the CCTV utility surveys on Mornington Terrace, Clarkson Row and Mornington Crescent last month. We have now rescheduled these surveys for the 12 to 14 May.
We will require footway closures, temporary traffic lights and parking bay suspensions to carry out the surveys. Please see 6 May notification update below for more information.

Trial holes on Park Village East – 8 to 12 March

We will carry out two trial holes within the planter on Park Village East to finalise the design for the upcoming ground strengthening works to the Network Rail retaining wall. We will carry out these works during core hours and require closures to sections of the footway between Parkway and Mornington Street Bridge. Please see map 2 in the PDF notice for details.

Installing ground monitoring equipment on Park Village East – 8 March to 7 May

We will install ground water monitoring equipment within the footway and carriageway on Park Village East. The work will take place during core hours and will involve closures to the footway and carriageway and parking bay suspensions. Having completed the first stage, we have now revised the works programme. We will carry out the next two stages at the same time to complete the works earlier and shorten the duration of the impact on residents. Please see notification update below.

UKPN phased lane closure from February

UKPN are currently excavating trenches to install electricity cables along Park Village East as part of an ongoing phased work programme. See Map 2. The works began on 1 February and are expected to continue until 31 March on Park Village East after which the team will move to Mornington Street bridge and Mornington Terrace. There will be closures to sections of the southbound lane between Stanhope Street and Mornington Street Bridge and parking bay suspensions as works progress. View UKPN’s original notice here.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]