Notice of utilities diversion works in Gordon Square

Work item: HS2-MW-MD-Ph1-Eu-St-S3-UT-1-18/11/2022

Work Item Summary

Project Phase
Phase 1
Location
Gordon Street
Contractor
Mace Dragados JV
Type of works
Utility works / surveys
Estimated Start Date
05/12/2022
Estimated End Date
10/04/2023

What we are doing

Utilities duct installation works will take place during December on Gordon Square, Endsleigh Place and Tavistock Square

As part of HS2 works, new routes for utilities need to be created ahead of the removal of old services. From 5th December new utilities ducts and access chambers will be constructed as indicated in the document below.

Work areas will be surrounded by temporary fencing and have traffic management measures in place. We will minimise noise using acoustic blankets on fencing surrounding the works when we are breaking out the road surface.