Notice of utilities diversion works on Byng Place and Torrington Place

Work item: HS2-MW-MD-Ph1-Eu-St-S3-Prog-works-1-13/01/2023

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Byng Place, Camden
Worksite Name
Euston Station
Contractor
Mace Dragados JV
Type of works
Utility works / surveys
Estimated Start Date
16/01/2023
Estimated End Date
05/02/2023

What we are doing

Utilities diversion and duct installation works will take place during January and February in Byng Place and Torrington Place.

As part of HS2 works, new routes for utilities need to be created ahead of the removal of old services. From 16 January to 5 February new utilities ducts and access chambers will be constructed in Byng Place and Torrington Place as indicated on the map below.

The road will be closed to vehicles with traffic being diverted. Cycle access will remain open. The work area will be surrounded by temporary fencing and have traffic management measures in place. We will minimise noise using acoustic blankets on fencing surrounding the works when we are breaking out the road surface.
Subsequent phases of works will take place on Gower Street, Upper Woburn Place and Euston Road. The dates for these works are still to be agreed. We will issue a notification when these dates have been confirmed.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]