Work item: HS2-EW-LM-Ph1-Bir-Cur-St-N4-UT-6-17/12/2020
Work Item Summary
- Project Phase
- Phase 1
- Region
- Birmingham, West Midlands
- Location
- Birmingham
- Contractor
- LM JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 18/01/2021
- Estimated End Date
- 30/06/2021
What we are doing
We’ll be carrying out works on Andover Street
Over the coming months, we’ll continue to work on roads in central Birmingham as we carry out a programme of utility diversions and prepare for the construction of HS2’s Curzon Street Station and the railway.
To carry out the utility works safely, we need to manage traffic in the local area. This will include a phased road closure on Andover Street. We’ll carry out the works in phases, rather than all at once to maintain access to frontages and to keep disruption to a minimum.