Notice of utilities work to the West of Euston Station
Work item: HS2-MW-MD-Ph1-Eu-St-S3-UT-TW-02-26/01/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Robert Street, Western Avenue
- Worksite Name
- Euston Station
- Contractor
- Mace Dragados JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 26/02/2024
- Estimated End Date
- 30/05/2024
What we are doing
Watermain commissioning Works
As part of our essential programme of utilities works, we will complete and commission the new 1000mm water main with works taking place over three months in Cumberland Market and Robert Street.
These works will commence on Monday 26 February 2024 until late May 2024. Working hours will be 8am – 6pm Monday to Friday, with occasional night time working when required.
We will ensure every effort is made to keep unnecessary noise to a minimum. Please note there will be no disruptions to local services.
Traffic Management will be in place for these works as detailed below, with pedestrian access being maintained at all times.