Notice of utility and construction works on Harvil Road
Work item: Ref HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-11/08/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Harvil Road
- Worksite Name
- Copthall
- Contractor
- SCS JV
- Type of works
- Construction, Utility works / surveys
- Estimated Start Date
- 30/08/2022
- Estimated End Date
- 05/09/2023
What we are doing
What we are doing
From 30 August 2022 to 5 September 2023, we plan to complete major utility diversion works and realign a section of Harvil Road.
We will be carrying out the main utility works and constructing the new road realignment simultaneously. The works will involve:
Installation of Water Main and communication ducting
Diversion of existing utilities into new utility corridor
Chamber construction (water and communication)
Existing road demolition
Highway & drainage construction
Surfacing, white lining, and street furniture
Site fencing realignment
The overall scheme will be completed in three phases between late August 2022 and early September 2023, with the main construction work taking place within our construction site boundaries on Harvil Road.
How these works might affect you
30 August to 15 October 2022: Installing of water main and communications cabling (BT) on Harvil Road either side of the carriageway opposite the SCS gate 1 site entrance
Four-way traffic lights on Harvil Road, southbound and northbound between oil depot and Shorthill Cottage
We will install a north and southbound priority narrowing lane as a safety measure due to the proximity of services
16 October to 27 November 2022: Installation of the remaining section of the water main in order to complete the connection
Four-way traffic lights on Harvil Road, northbound between Oil depot and Skip Lane
There will be a northbound lane closure on Harvil Road along the section of Skip Lane
We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way. We will ensure that disruption is kept to a minimum.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]