Notice of utility construction works Attleboro Lane, Water Orton
Work item: HS2-MW-UT-Ph1-Ar-No-N1-Prog-Works-17-12/02/2024.
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Water Orton
- Worksite Name
- Attleboro Lane
- Contractor
- National Grid Electricity Distribution (NGED)
- Type of works
- Construction
- Estimated Start Date
- 12/02/2024
- Estimated End Date
- 30/09/2024
What we are doing
We are writing to make you aware of the next stage of work that will be undertaken by National Grid Electricity Distribution (NGED) to reroute domestic electricity supplies required for the construction of the new railway line.
To construct the new railway, it is necessary to remove an old underground cable and replace it. The cable runs from the east of the existing HS2 construction compound to the west.
This work is being done in conjunction with the electrical cabling work previously advised to you by Balfour Beatty Viinci, which is due to start on Monday 29 January.
Access for staff and machinery will be through the existing HS2 entrance.
The works will be in a construction area that will have no impact on the local community, however there will be a lane closure for one day on Attleboro Lane. The date for this lane closure is unknown but will be advised to you nearer the time.
Our normal working hours will be Monday to Friday 8 am to 6 pm and Saturdays 8 am to 1 pm. Our contractors may also be on site for set-up and shutdown either side of these times, you may see security checks outside of these hours.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]