Notice of utility diversion works, Addison Road
Work item: HS2-EW-FUS-Ph1-Ar-Ce-C2-UT-25-08/03/2020
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Steeple Claydon
- Contractor
- Fusion JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 05/10/2020
- Estimated End Date
- 31/03/2021
What we are doing
Before the main construction works for the railway begins, we need to divert an existing Anglian Water sewer pipe. This pipe is located to the west of Addison Road, near to Shepherd’s Furze Farm. The sewer pipe will be locally diverted below the currently disused Grand Central main line.
This will be achieved using a construction technique called directional drilling. This avoids large open excavations and allows an undertrack crossing, (UTX) to be delivered with the least disruption.