Notice of utility diversion works – National Exhibition Centre, Birmingham
Work item: HS2-MW-Cadent-N1-UT-23-15/05/2025
Work Item Summary
- Project Phase
- Phase 1
- Region
- Birmingham
- Location
- Interchange Station
- Worksite Name
- NEC
- Contractor
- Cadent Gas
- Type of works
- Gas pipeline diversion
- Estimated Start Date
- 02/06/2025
- Estimated End Date
- 17/10/2025
What we are doing
Cadent will be starting work to move the pipeline within the National Exhibition Centre (NEC) complex in June 2025.
The work will involve:
• Securing our working area and compound off Pendigo Way with
fencing
• Digging a trench for the new pipeline off Pendigo Way
• Welding the pipe together then installing it in the trench
• Connecting and testing the new pipe
Work will take place within the NEC complex only. Please note, there will be no on-site lodging.
Cadent expects that the work will be completed by early October 2025.